Location : Riverside County, CA

Salka Cabazon Wind Farm

The Salka Cabazon wind farm is located in Palm Springs area, is an operating facility with a capacity of 37.4 MW and was built in the 1990s. It has been in operations since 1999.

  • Salka acquired Cabazon, a 37.4MW project in October 2023 in Riverside County. The farm consists of 50 turbines; 49 Zond Z48 and 1 RRB 47.

  • With a capacity of 37.4 MW, the wind farm is expected to power more than 11,000 homes and remove 48,749,400 tons of CO2.

Extreme Sports Bike
Extreme Sports Bike
Extreme Sports Bike
Extreme Sports Bike

Status

— Operational —

Facility Megawatt Capacity 37.4 MW
Site Control 375 acres under contract
PPA City of Riverside
Technology Wind
Commercial Operating
Utility Southern California Edison
Equipment 49 Zond Z48 and 1 RRB 47
Salka